Bibiyana gas plant go maintaennance from 15 to 20 October

Chevron Bangladesh Block Twelve Ltd. plans to perform it’s scheduled maintaennance and upkeep of the Bibiyana gas plant during the upcoming Eid and Durga Puja Holiday’s from 15th October to 19th October 2013. as a part of the maintenense, there will be a temporary halt in production from the Bibiyana gas plant. The operation has been timed to coincide with the Holiday closure as national consumption will be at lowest at this time period. However, the exact shutdown timing may very based on the energy demand during that period. from Bibiyana now supply 812 MMCFD gas.
During this time, gas production from Chevron’s Jalalabad and Moulavibazar facilities will be maximized. According to the tentative schedule, we anticipate full flow to start from 20th october 2013.

Bangora gas field also go maintaennance from 21 to 25 october. Bangora now supply 110 mmcfd gas.

 